Sewer Project

The US 13 sewer rehabilitation project involves installing a small carrier pipe into a larger host pipe a.k.a “sliplining” for 15,400 linear feet with no anticipated disruption of sewer services. The “sliplining” method will allow work to occur in the median with the existing pipe; therefore, the project will only involve temporary and limited traffic disruptions. This would include: temporary lane and turn lane closures.

Project Information

US 13 SEWER REHABILITATION PROJECT

  • View Project Flyer
    View Project Flyer
  • View Project Map
    View Project Map

The project area and construction sequence will start south at Garden Lane and move north up to West Denney’s Road on US 13 (North Dupont Highway). The project is anticipated to be complete within five months and will begin the last week of June, weather permitting. Multiple presentations and workshops are being conducted to provide project information to the Community. Please see the following presentation opportunities below:

Kent County Levy Court Presentation

Kent County Levy Court Administration Building 555 Bay Road, Levy Court Chambers, Dover Tuesday, June 18 at 6:00 pm

View Project Presentation
View Presentation

Outreach Open House Workshop #1

Kent County Levy Court Administration Building 555 Bay Road, Room 220, Dover 4:00 - 6:00 pm (presentation at 5:30) Wednesday, June 26

View Project Presentation
View Presentation

Outreach Open House Workshop #2

Delaware Agricultural Museum 866 North DuPont Highway, Dover 4:00 - 6:00 pm (presentation at 5:30) Thursday, June 27

View Project Presentation
View Presentation

Project Map/Area

US 13 SEWER REHABILITATION PROJECT

The project area and sequencing starts at Garden Lane and moves north up to West Denney’s Road on US 13 (North Dupont Highway). Construction is taking place in phases as shown on the map above and more detailed below.

# #

PHASE 1

Phase 1 is sectioned into two parts: 1A is from Garden Lane to North Street and 1B is from North Street to the Dover Mall Access Road

# #

PHASE 2

Phase 2 is sectioned into two parts: 2A is from the Dover Mall Access Road to the State Police Entrance location and 2B is from the State Police Entrance location to West Denney’s Road.

#

PHASE 3

Phase 3 is West Denney’s Road

Notifications

Project Notifications, Press Releases and Monthly Reports

Notification Flyer
Sign up for Notifications

All project notifications, press releases and monthly reports with the most up to date information can be found here. These are placed in chronological order with the most recent document on top. If you are interested in receiving up to date project email notifications, the notification subscription form can be found in this section to complete and send in for processing.

Traffic Cameras

Check out the current traffic and highway conditions along the US 13 Sewer Rehabilitation Project route with Deldot's US-13 Traffic Cams.

Point of Contact

US 13 SEWER REHABILITATION PROJECT

  • Address:

    614 N. Dupont Highway Dover, DE 19901

  • Phone No:

    (302) 318-1139

  • Email Address:

    project.outreach@kci.com

Kent County has contracted with KCI Technologies Inc. to provide continue outreach management for the duration of the project. KCI has created a dedicated project phone line and email address to support any concerns or questions the Community may have during the project. All calls and emails will be answered or first contact provided within a reasonable time upon receiving a voicemail message or email. Normal answering service hours are Monday – Friday from 8:00 am to 5:00 pm, unless otherwise determined based on the need of the project. All calls will be tracked and included in the monthly project reports. The dedicated contact options are provided: